The DADU Feasibility Checklist: 10 Things to Confirm Before You Build in Seattle
The Checklist That Saves You From Expensive Surprises
The most costly mistakes in DADU projects share a common cause: homeowners committed to a design — or a contractor — before they confirmed the basics. They assumed their lot could support the project they had in mind. They did not check their utility connections. They did not know about the easement running through their backyard.
This checklist covers the ten things every Seattle-area homeowner should confirm before they invest in architectural design or sign a construction contract. Some of these items you can research yourself. Others require a professional analysis. All of them matter.
Work through this list before you spend a dollar on design, and you will move into your project with confidence instead of surprises.
Item 1: Confirm Your Zoning District
DADUs are permitted in Seattle's Neighborhood Residential zones — NR1, NR2, and NR3 — and in some Lowrise zones. Before anything else, confirm that your property is in a zone where a DADU is allowed.
You can look up your zoning designation on Seattle's online zoning map at the city's GIS portal. Enter your address and confirm the zone designation. If your property is in a Lowrise zone, the applicable DADU rules may differ from the standard NR zone requirements — a professional zoning analysis is worth the investment.
If your property is in an unincorporated area of King County rather than within a city's limits, the applicable rules are those of King County's zoning code, not Seattle's or any other city's.
Items 2 and 3: Calculate Your Lot Size and Existing Coverage
Item 2: Confirm your lot size. Your lot's square footage determines your maximum allowable lot coverage and, in some cases, your setback requirements. You can find your lot size on your property tax records or on the King County Assessor's website. For precise measurements, a survey is the most reliable source.
Item 3: Calculate your existing lot coverage. Add up the footprint of every structure on your lot — your house, garage, sheds, covered patios, and any other roofed structures. Compare that total to your allowable maximum (35 percent of lot area for lots 5,000 square feet or larger in Seattle's NR zones). The difference is the square footage available for a DADU footprint.
This calculation is one of the most commonly underestimated steps in DADU planning. Homeowners frequently forget to include covered patios, detached garages, or storage sheds — and are surprised to discover they have less room than they thought. A professional coverage calculation, based on a current survey, is the only way to know your number with certainty.
Items 4 and 5: Map Your Setbacks and the 10-Foot Separation Rule
Item 4: Map your setback envelope. In Seattle's NR zones, a DADU must maintain a minimum of 5 feet from each side property line and 5 feet from the rear property line (0 feet if you back up to a public alley). The DADU cannot be located in the front yard. Draw these setback lines on a sketch of your lot to see where the buildable area actually is.
Item 5: Apply the 10-foot building separation rule. There must be a minimum of 10 feet of clear separation between the exterior walls of your primary residence and the new DADU. This is measured from the closest points of the two structures. On smaller lots or lots with large existing homes, this rule can significantly constrain where a DADU can be placed — or eliminate certain locations entirely.
Combining your setback envelope with the 10-foot separation requirement gives you a rough picture of your buildable zone. A professional site plan, drawn to scale, is the most reliable way to visualize this accurately.
Items 6 and 7: Check Height Limits and Power Line Clearances
Item 6: Confirm your height limit. Seattle's DADU height limits depend on your lot width and your chosen roof style. For a standard lot 30 feet or wider, a flat or shed roof allows 14 to 16 feet; a pitched roof allows 18 to 20 feet. Taller structures may require increased side setbacks. Confirm the specific limits that apply to your lot before you commit to a design direction.
Item 7: Check for overhead power lines. Seattle City Light enforces radial clearance zones around overhead high-voltage distribution lines. If your backyard has overhead power lines, your DADU must maintain a minimum clearance — typically 10 to 14 feet — from those lines. This can significantly constrain your buildable area and in some cases requires underground utility relocation before construction can proceed.
Power line clearances are one of the most commonly overlooked constraints in DADU planning. A site visit that maps the location and height of any overhead lines in your backyard is an essential part of a thorough feasibility analysis.
Items 8, 9, and 10: Trees, Utilities, and Easements
Item 8: Identify significant trees. Seattle's tree protection ordinance requires retention of exceptional trees — generally 24 inches or more in diameter at breast height — and establishes critical root zones that restrict where structures and heavy equipment can be placed. Walk your lot and identify any large trees. Their location and root zones may constrain your buildable area more than the setback rules do.
Item 9: Review your utility connections. Your DADU will need connections to water, sewer, and electrical service. Confirm that your existing service connections have sufficient capacity to support a second unit, and identify where new connections would need to be made. In some older Seattle neighborhoods, water and sewer infrastructure upgrades are required before a DADU can be connected — a cost that needs to be factored into your project budget.
Item 10: Check for easements. Utility easements, access easements, and other encumbrances on your property title can restrict where structures can be built. Pull your property's title report and review it for any easements that run through your lot. An easement through your backyard can eliminate what looked like a perfectly viable DADU location.
Working through all ten items on this checklist is exactly what a professional feasibility study does — systematically, accurately, and in writing. At DADU Solutions, our Pre-Design Feasibility Study at $1,900 covers every item on this list and delivers a written report that tells you exactly what you can build, where you can build it, and what constraints will shape your project. It is the foundation of every successful DADU project — and the most important investment you will make before you break ground.